Sunday, January 07, 2007

Update

This weekend I took some measurements and counted things that I need to buy (door stops, hooks for behind doors, etc). I also got the serial numbers off the appliances so I can send in the rebate paperwork and swapped out some light bulbs. Here is what is supposed to take place over the coming week:

-tile is supposed to be installed in the guest bath shower and then the master shower
-the plumber is supposed to be back to install fixtures such as the upstairs toilets, faucets, bathroom sinks, the big tub, the showers (after the tile), and the dishwasher
-the rest of the appliances should be installed (the dishwasher and stove)
-a concrete sub is fixing the entry to the east garage door, pouring a pad at the bottom of the deck stairs, fixing the holes in the basement (from the new plumbing) and capping the stairs to the basement (weather permitting)
-the floor sub is supposed to buff and poly the second floor hardwoods (which was supposed to happen last week)
-the cabinet maker is delivering the master bedroom bed and modifying the microwave cabinet (depending on the floor sub)
-the remaining light fixtures will be installed

Granted, I don’t really think all of these will get done but they could and should. I didn’t get anything moved over this weekend because things aren’t done enough over there. Hopefully this coming weekend I will be able to do that. I really want to avoid the last minute rush to get moved in if I can avoid it.

0 Comments:

Post a Comment

<< Home